Cladding & Curtain Walling
21 April 1989
<<
continued from previous page
Corporation. The Development Corporation had carried
out tests based on local weather criteria and were
satisfied with the system's performance.
However, there were still problems to overcome: the
development of the design and detailing of the material,
the integration of doors, windows and roof covering
and the potential cost increases as a result of these
factors.
This is the stage when the contractual problem arose.
Most systems are only supplied by the manufacturer
or agent. Although part of the system the ultimate
"design" is the reponsibility of the erector,
who at this point in time is, like the supplier, not
yet appointed.
The main contract was to be the result of competitive
tender and the client did not wish to nominate any
subcontractors or suppliers. It was however permissible
to name the product in the tender document but the
erector of the system had to be selected by competitive
tender.
This made it impossible to develop the detailed
design of the system prior to a main contractor being
appointed. This meant there could be a potential delay
at the start of the contract, and accurate costs would
not be known until tenders were received.
Fortunately all external apertures and the roofing
element formed part of the one element for tender
purposes. All the component parts of this element
- the external envelope - could be "named"
and their erection carried out by one domestic subcontractor
who would be part of the main contractor's competitive
tender.
The development of the external envelope design virtually
ceased during the design process when input from the
erection subcontractor was required. Very little additional
information was forthcoming from the supplier at this
stage since without financial commitment he was unwilling
to give further information on his product.
When tenders were received and a contractor appointed
the responsibility for the design of the system had
passed to the main contractor. The main contractor
was by then satisfied that the cladding subcontractor
could carry out what was required and the supplier
was satisfied that the cladding subcontractor could
erect the system in question.
It is several years since our involvement with the
laboratory building. We were ultimately satisfied
with the results in the end despite the rather involved
contractual/design process.
In early 1988 we were commissioned to the Calders
in Edinburgh, to overclad a high rise, local authority,
blocks of flats and again the circumstances were very
similar to the laboratory building.
The majority of the initial selection of systems
were over-budget and a simpler adaptable system which
had been used locally consisting of profiled sheeting
with coloured flashings was preferred. The client
did not wish to nominate a supplier but preferred
to name the system to be erected and to state that
it be erected by the system designer's approved contractor.
So, like the laboratory building, during the detailed
design stage the detailing of the cladding ceased.
Full working drawings were not available until the
main contract was let.
Is the need for this excessive selection and deign
process a result of our client not having adequate
funding to select a system which has been developed,
tried and tested? And does the continuing development
of cladding materials and their use in situations
of competitive tender where nominations are not permitted
necessitate the processes outlined? The answer must
be yes to both questions.
The main contractors in both examples have accepted
the naming of systems and have ultimately taken design
responsibility for these systems. If these main contractors
refused to accept responsibility for named systems,
i.e. demanded nomination, then letters of intent could
be issued by clients and detailed design could be
undertaken at the appropriate stage in the design
process.
However, the likelihood of this happening is slight
since there will always be a suspicion that taking
such a stance will result in exclusion from the tender
list.
A united front may help - let's hope it happens before
our next cladding project •